We have not been able to go inside the house for a really long time now and as a result we hardly could conceive what is going inside. Today when we had been to the front of the house we saw some empty cartons related with fans, heating globes, toilets seats and things like that. Looking at these things we could perhaps make out that the following would have been done, but we have yet to receive the status report from our SM.

  • Toilet seats installation completed
  • Electricals near completion as we could see the points outside to be almost completed. May be some work is left inside. No idea!
  • Painting inside should be complete, but not sure...
  • Heaters/Exhaust Fans installation on way in baths
  • Ground floor painting partially done (not a good work though). 

Pending work:
  • Cupboards installation
  • Toilet shower screens
  • Spa installation ??
  • Outside plumbing
  • Outside painting
  • Painting on the portico
  • General cleanup
  • Wooden Flooring/Carpeting
  • Whirleybird
  • Appliances installation
  • Front door painting (another coat??)
  • Fireplace installation ??