Friday, June 21, 2013

Day 92: Disappointing Progress



There has not been much to report on for the last few weeks and it has been disappointing run for us. Had a call from Metricon on Friday to find about the frequency of the updates that we get  from the SM. I was positive in my response, but deep down I am thinking I should not have been that nice looking at the progress for the last one month. The whole thing seems to be stalled without any reason. I have been getting the same update for so many weeks. I have been told that by the end of the next week i.e. 28th June the following things will be done:
  1. Rendering on the outside walls
  2. Painting on the walls
  3. Downpipes installation
  4. Painting of the downpipes
  5. Removal of the scaffoldings




No comments:

Post a Comment